When the St. Mary pipelines were built to provide water in 1915 to northern Montana, construction workers hit winter, too.
Then, said Jennifer Patrick, the project manager for the Milk River Irrigation Project Joint Board of Control, they had no choice but to wait — it was simply too cold to pour concrete.
One-hundred ten years later, more than 18,000 people depend on the water that’s diverted near Babb from the Milk River in order to irrigate some of the state’s richest farmland.
Last summer, one of the huge lines used for collecting water failed, dealing a blow to farmers, ranchers and residents even as far away as Canada. Federal leaders in Congress and state leaders rushed to figure a solution. That funding was held up and in limbo until early Thursday evening when U.S. Sen. Steve Daines of Montana said that he had worked with the Department of the Interior to re-approve the project.
Funding had been uncertain, due to the federal funding freeze announced by President Donald J. Trump, and because the project was part of the Bipartisan Infrastructure Law — Infrastructure Investment and Jobs Act, often targeted by the new administration as an example of waste.
“The St. Mary siphon failures this past summer were catastrophic. Farmers, ranchers and Montanans across the Hi-Line depend on these siphons for a reliable water supply and I’m glad the President and Secretary (Doug) Burgum share my goal of fully repairing the siphons as soon as possible,” said Daines.
Yet, despite temperatures that have dipped below zero and stayed stubbornly there, Patrick said the construction project is on schedule as workers use the latest chemical mixtures of concrete to pour in colder weather. That has made a big difference in how quickly the project is progressing. Patrick said large temporary heat shacks are being used so that welders can continue to stay on schedule. Sometimes, that means a temperature swing of more than 140 degrees from outside to inside.
All of the work would have come to an immediate halt, she said, if not for the forward-looking help of state lawmakers and the Gianforte administration, which made the project eligible for a revolving loan program. Right now, a $35 million loan is paying the bills keeping the work moving. With news of the funding release, the plans and construction should move ahead.
The Daily Montanan also reached out U.S. Sen. Tim Sheehy for comments but did not receive a response.
“We’re paying a lot for winter construction, but we have to get this going,” Patrick told the Daily Montanan.
The totals for the overall project cost is estimated at $78.9 million.
Pro-Pipe Construction from Frenchtown is handling the welding of the 90-inch steel siphons.
“So far, 3,900 of the planned 6,444 feet have been installed,” Patrick said in a written update.
The timeline originally had set a late summer 2025 completion date, and currently Patrick said the project is on time.
“Given the freezing temperatures, special measures — including blanketing, heating and modified concrete mix designs — are being used to making the integrity of the pours. So far, test results indicate these techniques are working as planned,” Patrick added.
Patrick said the work is continuing, thanks in large part to a loan agreement that was pushed by Sen. Mike Lang, R-Malta, and Rep. Paul Russ, D-Havre, who made the measure part of House Bill 6 in 2023.
“Without state funding and all the help we’ve gotten from the budget office and the governor, we would not be moving forward,” Patrick said. “We’re obviously not the only project with a federal funding hold. But we’re a good project, and we’re confident in a review, we’re just held up with others.”
She said that a funding lapse of three months is about as long as the project could survive on state money alone.
“Even a week of water is important, and every day the construction crews can push it is time we can get,” Patrick said. She did say, though, a heavy snowfall could delay the project for weeks.
She said the impacts of the project finishing late or being delayed would be an economic loss of $60 million to $70 million annually. However, she said that many people don’t realize how many farms and communities, mostly clustered around Montana’s Hi-Line, would be hurt.
“People say, ‘How many miles?’ Patrick laughed. “This serves 700 miles of community.”
Darrell Ehrlick is the editor-in-chief of the Daily Montanan, a nonprofit newsroom.
News Source : https://dailyinterlake.com/news/2025/feb/22/st-mary-project-moving-ahead-daines-says-interior-has-approved-the-project/
Other Related News
02/23/2025
Photos from the Whitefish Skijoring event held at 1530 W Springcreek Road on Saturday Feb...
02/23/2025
Peak Fit a fitness and wellness center that opened in Whitefish two years ago has expande...
02/23/2025
After a period of uncertainty state and city officials say regional infrastructure projec...
02/22/2025
Federal workers received an email stating that they must reply with a list of their accomp...
02/22/2025